REINFORCEMENT/REHABILITATION OF DILAPIDATED ELECTRICITY NETWORK AT OKPA IVIE-OLEH COMMUNITY, ISOKO SOUTH LOCAL GOVERNMENT AREA

Reinforcement/Rehabilitation of Dilapidated Electricity Network at Okpa Ivie-Oleh Community, Isoko South Local Government Area
New Projects

Project Gallery (1)

Project Description

The reinforcement and rehabilitation of the dilapidated electricity network at Okpa Ivie-Oleh Community, Isoko South Local Government Area, by Rt. Hon. Sheriff Oborevwori, is aimed at improving the reliability and efficiency of electricity supply within the community. The scope of works includes: installation of 1No. 300kva, 11/0.400kv distribution transformer, 1No, 800a 4-way feeder pillar (on site), erection of 20No. (8.54m) LT reinforced concrete poles and stringing of low tension overheads lines.
The project will rehabilitate damaged electrical infrastructure, improve power distribution capacity, reduce frequent power interruptions, enhance the safety and functionality of the electricity network, support households and businesses that depend on electricity, and contribute to improved socio-economic development and living conditions in Okpa Ivie-Oleh Community.

Sustainable Development Goals (SDGs) Impacts

Affordable and Clean Energy

Affordable and Clean Energy

Industry, Innovation and Infrastructure

Industry, Innovation and Infrastructure

Sustainable Cities and Communities

Sustainable Cities and Communities

Project Information

Contract Period

12 WEEKS

Progress

0%

Ministry/MDA

RURAL DEVELOPMENT AGENCY

CNO Reference

DSPPC/CNO/2237

Year

2026

Date Awarded

17/08/2026

Expected Completion

02/11/2026

Location (LGA)

Isoko South

Address

Okpa Ivie-Oleh Community

Contractor

ROYAL PEAK SYSTEMS

Category

Works

Coordinates

Lat: 5.40429680, Long: 6.19513200,